The 20-year power purchase agreement announced by Google and Constellation Energy will enable investments in new equipment and technology at 11 Constellation-owned nuclear units in Illinois, Pennsylvania, and New Jersey, the companies said. The improvements in thermal and electrical efficiency achieved will result in adding new capacity to the grid, expanding total electricity generation available across the PJM footprint. The agreement helps sustain roughly 4,400 existing jobs, creates approximately 7,200 new construction jobs during the building period and represents more than USD4.3 billion of new investment by Constellation, the company said.
The 890 MW of incremental capacity delivered through this collaboration equals the output of three or more small modular reactors (SMRs) or a large new conventional reactor.
The companies have also entered into a 15-year energy supply agreement for an additional 2,700 MW in PJM's fleet, which Constellation says will provide revenue certainty, ensuring existing assets remain economically viable without taking resources off the grid.
Google and Constellation have also agreed on a strategic framework to evaluate opportunities to develop new clean generation, storage and demand response across the USA to support Google's growth, prioritising near-term efforts in the PJM region. Constellation has selected Google Cloud and Gemini Enterprise under an expanded five-year technology alliance which aims to use AI to reduce the costs of new infrastructure, improve performance, ensure enough power is generated to meet rising demand, and safeguard the energy grid.
Nuclear uprates can be achieved through measures such as modernising and upgrading turbines, steam generators, and digital control systems at operating plants. This can deliver substantial capacity gains without the multi-year timelines or interconnection bottlenecks associated with greenfield construction, providing a practical, near-term mechanism to deploy firm, clean megawatts to meet increasing electricity demand, Constellation said.
The 890 MW of incremental capacity that will be delivered through the collaboration is equivalent to the output of several small modular reactors or a large new conventional reactor. The initiative directly advances the goals of the US government's UPRISE programme to maximise electricity output from existing nuclear infrastructure through public-private collaboration, the companies said. The first uprate is expected to be delivered by 2028.