Power & SitesUnited States

TeraWulf Doubles Contracted Power at Muskie Data Campus to 1 GW

Credited to Converge Digest · convergedigest.com

Useful
Photograph · Converge Digest

TeraWulf has amended its electric service agreement with Kentucky Power, an American Electric Power (AEP) company, to increase contracted power capacity at its Muskie Data Campus in eastern Kentucky from 500 MW to 1 GW. The agreement also accelerates the planned delivery of the campus’s second 500 MW phase from 2030 to 2029, while the initial 500 MW remains targeted to begin ramping in 2028.

The amendment strengthens TeraWulf’s power position at Muskie as the company develops the site for large-scale AI and high-performance computing workloads. Importantly, the 1 GW figure represents contracted electric service capacity rather than operating data-center capacity. The second phase remains subject to Kentucky Public Service Commission approval and Kentucky Power’s construction schedule.

TeraWulf Muskie Data Campus — Key Points

• 1 GW contracted power — amended Kentucky Power agreement doubles the electric service commitment from 500 MW. • First 500 MW: targeted to begin ramping in 2028. • Second 500 MW: planned delivery moved forward from 2030 to 2029. • Regulatory dependency: second phase remains subject to Kentucky PSC approval and Kentucky Power’s construction schedule. • Kentucky Power is developing a 765-kV / 345-kV substation connected to the regional transmission network. • TeraWulf says it is evaluating the site’s potential to eventually support up to 2 GW, subject to additional utility planning, infrastructure and agreements. • Muskie was acquired by TeraWulf in May 2026 for development as an AI/HPC campus.

TeraWulf acquired Muskie in May 2026. The approximately 308-acre site is located in Grayson, Kentucky, within the EastPark Industrial Park. Kentucky Power is developing a 345-kV substation connected to the existing 765-kV transmission network to provide the high-voltage infrastructure required for hyperscale development.

When the acquisition was announced, TeraWulf targeted the initial 500 MW for the second half of 2028 and another 500 MW for the second half of 2030. The new agreement therefore does more than formalize additional capacity under the electric service agreement: it moves the second phase forward by approximately one year.

TeraWulf Chairman and CEO Paul Prager said customer interest in Muskie has been strong and that securing the additional 500 MW gives the company greater flexibility in discussions with prospective customers. No tenant or AI compute customer was identified for Muskie in the October 5 announcement.

The company is also evaluating whether Muskie could ultimately expand to as much as 2 GW. That additional capacity has not been contracted and would require further utility planning, infrastructure and agreements.

The distinction between contracted power, planned power and delivered capacity is increasingly important as AI infrastructure developers announce multi-gigawatt development pipelines. TeraWulf now has an amended electric service agreement covering 1 GW at Muskie, but the first 500 MW is not expected to begin ramping until 2028, and the second 500 MW is planned for 2029 and remains subject to regulatory approval and utility construction.

There is also a useful clarification relative to TeraWulf’s earlier disclosures. Its Q2 2026 10-Q described the original arrangement as a 500 MW electric service agreement plus a separate 1,000 MW letter of agreement covering transmission infrastructure. Today’s announcement makes the commercial position clearer: the amended and restated electric service agreement itself has now been increased from 500 MW to 1 GW.

Muskie also complements TeraWulf’s separate Justified Data Campus in Hawesville, Kentucky, where Anthropic has committed to approximately 401 MW of critical IT capacity under a 20-year lease. That project is targeted to begin delivering capacity in the second half of 2027 and reach full delivery in early 2028.

The broader strategic theme is increasingly clear: TeraWulf is repositioning around large blocks of secured power, high-voltage transmission access and long-duration AI infrastructure deployments. At Muskie, the immediate milestone is not server deployment but the securing and acceleration of the utility infrastructure required to make gigawatt-scale deployment possible.

Core Business — Large-scale digital infrastructure for AI and HPC workloads

Muskie Campus — 1 GW contracted electric service in Grayson, Kentucky; initial ramp targeted for 2028

• July 6, 2026 — TeraWulf Lands $19B Anthropic Lease for 401 MW Kentucky Campus • August 17, 2025 — From Mining to AI: TeraWulf Secures Billions in Contracts, Plots 400 MW Growth