SK Eternix and Mastern Investment Management will develop a fuel cell-linked data center. The companies will flesh out the business model and assess its technical and economic feasibility.
SK Eternix said Oct. 8 it signed a memorandum of understanding (MOU) with alternative investment-focused asset manager Mastern Investment Management on Oct. 7.
The MOU was signed to develop a hyperscale artificial intelligence (AI) data center powered by fuel-cell generation facilities.
The companies will jointly pursue an independent, or off-grid, data center model in which fuel-cell generation facilities installed on the site directly supply electricity to the data center.
Fuel cells can be installed at high density even on limited sites. Their relatively short construction periods can reduce delays in securing power caused by the expansion of large-scale transmission networks. They have recently drawn attention as a power source for data centers, where electricity demand is surging with the spread of AI.
SK Eternix will oversee the supply of fuel-cell power. It will handle the entire process, from the engineering, procurement and construction (EPC) of generation facilities to establishing the power-supply structure and managing operations and maintenance.
Mastern Investment Management will oversee the overall development project. Its responsibilities will include securing data center sites and permits, reviewing development scale, design, establishing the investment structure, raising funds and attracting tenants.