Power & SitesUnited States
MISO asks FERC for a 120-day fast track for data centers that bring their own power

The Midcontinent Independent System Operator has asked federal regulators to approve a fast-track review that would study a large new power customer and the generation built to serve it side by side, in about 120 days.
In an Oct. 2 filing with the Federal Energy Regulatory Commission, in Docket No. ER27-25, MISO proposed what it calls the Large Load Addition Resource Study, or LARS. It would be open to loads of at least 200 megawatts paired with new generation in the same local resource zone, the planning areas MISO uses to set capacity requirements. MISO asked FERC to approve the changes effective Dec. 2 so the first study period can open in the first quarter of 2027. Comments are due next Friday, Oct. 23, according to FERC's notice of the filing.
MISO called LARS "a narrowly scoped but powerful process," while conceding that "the benefits of LARS are not free."
MISO, which runs the grid across 15 states and the Canadian province of Manitoba, says it needs the tool because demand is climbing. Demand in its region grew about 0.5% a year from 2009 to 2024. MISO's updated Reliability Imperative report, released in March, projects growth of up to 2.1% a year through 2044, driven by data centers, manufacturing expansion and electrification.
The filing also answers FERC, which found on June 18, in Docket No. EL26-70, that MISO's tariff may be unjust and unreasonable because it lacks interconnection procedures for generators serving "electrically proximate" large loads. MISO says LARS fills that gap for pairs that do not qualify for its zero-injection agreement for co-located plants, which is pending at FERC separately.
The entry terms are strict, and MISO says that is deliberate. Only the utility or other load-serving entity that will buy transmission service for the customer can file an application, though independent power producers can take part as the generator. An application must carry a non-refundable $250,000 deposit and a milestone payment of $30,000 for every megawatt of interconnection service requested; that payment is fully refundable if the project withdraws before signing its interconnection agreement. The generator and the transmission owner must agree on a connection point before applying. The generator can request no more than 150% of the load's peak demand, and the application must show both the plant and the load in service within three years, subject to an existing grace period of up to three more. MISO said the requirements are meant to admit only projects that are "shovel ready" and commercially viable.
MISO will take 10 applications in each of three study periods a year, in the order they are filed, which caps the program at 30 pairs a year. The generation study is meant to produce an interconnection agreement in about 120 days. The parallel load study, built on MISO's existing expedited review, runs about 90 days. Entergy backed the concept in September comments posted on MISO's website but called the cap "arbitrary."
The pairing is meant to stick. To apply, the generator needs a binding contract of at least five years with the utility or the customer, but the plant and the load must stay paired for 15 years once the load starts taking service. If the load leaves or the contract ends inside that window, MISO will cancel the generator's interconnection agreement after a transition period of up to a year, longer if the plant is moving through MISO's regular queue. Parties that withdraw after the study still owe for assigned network upgrades. After 15 years, the generator keeps its interconnection rights even if the load goes away. MISO said 15 years is a standard term for large-load contracts and long enough to deter developers from invoking a large load "as a pretext to bypass" the regular queue.
The design moved quickly. MISO introduced the concept in July with a 250 MW floor, then cut it to 200 MW after what it called "significant stakeholder feedback that many emerging data center and large industrial projects in the 200-250 MW range can have significant system impacts."
Not everyone is persuaded. In September comments on an earlier draft, posted on MISO's website, the grid operator's environmental sector, a group whose members include the Natural Resources Defense Council, Sierra Club and the Union of Concerned Scientists, said LARS "is not responsive to FERC's Show Cause Order" because it treats generation anywhere in a resource zone as close enough. It said a fast track that prioritizes large-load customers over all other end users "introduces serious discrimination concerns," and urged MISO to drop LARS for an alternative design or let it expire after a year.
MISO argues that LARS projects are kept out of its regular queue studies and use none of the transmission capacity available in them, so any effect on later queue projects "would only be positive." It said it will file a cost-shifting agreement and transmission service terms for large loads by Nov. 16.
At least 20 parties had moved to intervene by Oct. 13, including Entergy, Vistra, Constellation and NextEra Energy Resources.